Painting! Several volunteers (see photos) painted the upper floor ballroom, and it looks amazing. On October 3, 2026, volunteers took on the task of painting the upstairs area. Special thanks to LAKE CHELAN BUILDING SUPPLY for the donation of all the supplies and to RODDA PAINT for the excellent quality paint! On November 6, 2026, Precision Paint/Seth Hardin expertly painted the ceiling!
Phase five: With a newly acquired $100,000 grant from the state legislator, and your private donations, we will soon begin the renovations for the sidewalk, upstairs bathroom and outside main entry. Stayed Tuned and please donate. See our GoFundMe account on the Home page.
Completed Phases: Downstairs bathrooms, HVAC (heating & cooling), ADA Ramp, and painting! Please view the photo gallery of our projects - before, during, & after!
January, 2025 - May, 2025 - Phase one was the downstairs bathroom remodel. COMPLETED by contractor, Jeff Gerot (L&J Construction).
April, 2025 - June, 2025 - Phase two - COOL RED Air completed the upgrade & installation of the new HVAC system.
November, 2025 - May, 2026 - Phase three - K4 Construction completed the ADA Ramp!
November, 2026 - Phase four - Precision Paint, Lake Chelan Building Supply, Rodda Paint, and member volunteers completed the painting of the upper floor ballroom. Come check it out. It transformed the Grange.
Bathroom Demolition Begins - 1/15/25
Bathroom Demoliton Begins - 1-15-25
Bathroom Demolition Begins - 1-15-25
Cement Floor Removal - 1-23-25
Cement Floor Removal - 1-23-25
Screened off area - 1-23-25
Plumbing Access - 1-25-25
Bathroom Wall Removed - 1-25-25
Plumbing passes inspection! - 2/20/2025
Plumbing passes inspection! - 2-20-25
Plumbing passes inspection! - 2-20-25
Framing & concrete floor - 3-7-25
Framing & concrete floor - 3-7-25
Framing equipment - 3-7-25
Framing & Plumbing - 3-15-25
Framing - 3-15-25
Sheet rock - 4-11-25
Sheet rock - 4-11-25
Sheet rock- 4-11-25
Downstairs Bathroom Remodel
Downstairs Bathroom Remodel
Finished! The downstairs bathroom remodel is complete! Three separate private bathrooms.
Cement slab for HVAC- 4-23-25
HVAC system - perfect!
Day One! K4 Construction starts ramp projet. 11-18-25
Base Prep for ramp - 12-2-25
Footings for Concrete Ramp - 12-8-25
Footings-Concrete poured-12-10-25
Fixing Gutter, Pouring Concete - All in a day's work! 12-10-25
Forms are ready for concrete! 12-14-25
Forms are ready for concrete! 12-14-25
Forms Concrete Poured-12-17-25
Forms Concrete Poured - 12-17-25
Lower Ramp - 2-8-26
Lower Ramp - 2-8-26
Steel handrails installed - 4-4-26
Steel installed - 4-4-26
K4 Construction Crew! Thank you.
Getting oh, so, close to completion. 4-28-26
Concrete Ramp - 4-28-26
ADA Ramp! May 28, 2026 - Celebrate Success
Before the painting of the upper floor ballroom. 10-3-26
Before the painting began. 10-3-26
Prep work - 10-3-26
Painting - Good job Ry & Phyllis - 10-3-26
Almost done. Thank you Lake Chelan Building Supply!
The old "pinkish" color is forever gone. Thanks, Bill. 10-3-26
The walls are finished - Thank you Rodda Paint. 10-3-26
The walls are finished! Thank you Rodda Paint. 10-3-26
Ceiling is painted. Thank you Seth Hardin with Precision Paint. 11-7-26
The ceiling painted by Precision Paint! Thank you. 11-7-26
Ceiling Painted by Precision Paint. Thank you Seth Hardin. 11-7-26
Hardworking volunteer paint crew! Ry, Terrie, KJ, Phyllis, Jeff & Debbie. Thank you all.