ADA Ramp Timeline:
April 28, 2026 - Concrete ramp is complete, steel handrails installed. Doors to be changed directionally late next week. Again, K4 Construction is top-notch!
April 4, 2026 - The steel handrails have been installed. Concrete and finishing touches coming this week.
March 14, 2026 - The lower ramp is taking shape and 4K Construction is watching the weather for the rest of the concrete pour. In the meantime, steel railings and the upper ramp are being built off-site. See photos!
December 15, 2025 - Check out the photo gallery as we move swiftly into the ramp concrete pour. THANK YOU K4 Construction! Working in the rain and pumping water isn’t easy…. 4K gets it done!
December 10, 2025 - Forms are built and concrete poured for the footings and base of the ramp. Today, trees were trimmed away from the building. THANK YOU K4 Construction.
December 2, 2025 - Excavation portion removed tons of dirt, shrubs, irrigation lines, etc., before beginning the build. Great job, Will (K4 Construction)!
November 18, 2025 - We are proud to announce the start of construction of the ADA Ramp project by K4 Construction. Watch our progress here or stop by to check it out. We anticipate completion of this ramp by the end of March 2026. THANK YOU all for support and donations.
Completed Phases: Downstairs bathrooms and HVAC
January, 2025 - May, 2025 - Phase one was the downstairs bathroom remodel. COMPLETED by contractor, Jeff Gerot (L&J Construction).
April, 2025 - June, 2025 - COOL RED Air completed the upgrade & installation of the new HVAC system.
Bathroom Demolition Begins - 1/15/25
Bathroom Demoliton Begins - 1-15-25
Bathroom Demolition Begins - 1-15-25
Cement Floor Removal - 1-23-25
Cement Floor Removal - 1-23-25
Screened off area - 1-23-25
Plumbing Access - 1-25-25
Bathroom Wall Removed - 1-25-25
Plumbing passes inspection! - 2/20/2025
Plumbing passes inspection! - 2-20-25
Plumbing passes inspection! - 2-20-25
Framing & concrete floor - 3-7-25
Framing & concrete floor - 3-7-25
Framing equipment - 3-7-25
Framing & Plumbing - 3-15-25
Framing - 3-15-25
Sheet rock - 4-11-25
Sheet rock - 4-11-25
Sheet rock- 4-11-25
Downstairs Bathroom Remodel
Downstairs Bathroom Remodel
Finished! The downstairs bathroom remodel is complete! Three separate private bathrooms.
Cement slab for HVAC- 4-23-25
HVAC system - perfect!
Day One! K4 Construction starts ramp projet. 11-18-25
Base Prep for ramp - 12-2-25
Footings for Concrete Ramp - 12-8-25
Footings-Concrete poured-12-10-25
Fixing Gutter, Pouring Concete - All in a day's work! 12-10-25
Forms are ready for concrete! 12-14-25
Forms are ready for concrete! 12-14-25
Forms Concrete Poured-12-17-25
Forms Concrete Poured - 12-17-25
Lower Ramp - 2-8-26
Lower Ramp - 2-8-26
Steel handrails installed - 4-4-26
Steel installed - 4-4-26
K4 Construction Crew! Thank you.
Getting oh, so, close to completion. 4-28-26
Concrete Ramp - 4-28-26